Category Archives: 2011 Florida Statute Amendments of Development Regulations

Summary of some of the major changes to the Florida growth management statutes

The following is a summary of some of the major changes made by the 2011 Florida legislature to the state’s growth management laws. Most are from by HB 7207, which is now Chapter 2011-139, Laws of Florida.

  • Name. The name of the part II, chapter 163 act is changed from the “Local Government Comprehensive Planning and Land Development Regulation Act” to the “Community Planning Act.” §163.3161(1), F.S. This reflects the shift from State oversight to local government control of the planning and growth management process. The State’s new role is to focus on “protecting the functions of important state resources and facilities.” §163.3161(3), F.S.
  • Purpose. The Act’s purpose moves from “control future development” to “manage future development consistent with the proper role of local government.” §163.3161(2), F.S. A new purpose statement focuses on recognizing and protecting “the traditional economic base of the state, agriculture, tourism, and military presence” while also encouraging “economic diversification, workforce development, and community planning.” §163.3161(11), F.S. See also this Article for more on the purpose statements of the act.
  • Comprehensive Plans and Plan Amendments.
    1. Contents of Comprehensive Plans. The requirements for what a comprehensive plan must contain are substantially rewritten, but are not as completely different as they would appear to be. Much of what appears to be new language is language moved, with some modifications, from other sections or subsections or is from the rules of chapter 9J-5, Florida Administrative Code (which has been repealed). See the Requirements for Florida comprehensive plans article for more details.
    2. Plan Amendment Process. See the article Process for review and adoption of plan amendments.”
      1. Twice a year limit. The limit restricting plan amendments to no more than twice a year is deleted. Previous §163.3187(1)(a), F.S.
      2. Expedited state review process. An expedited state review process, based on the previous §163.32465(2) pilot program, is added. This expedited process applies to all plan amendments except small scale amendment (which may be processed under this process or under the provisions of §163.3187) and plan amendments in an area of critical state concern, that propose a rural land stewardship area or a sector plan, that update the comprehensive plan based on a §163.3191 evaluation and appraisal, or that are for a new plan for a newly incorporated municipality. These other exceptions must follow the “State coordinated review process.” §163.3184(2) and (3), F.S. See the article Process for review and adoption of plan amendments for more.
      3. Administrative challenges. The language of former §163.3184(9) and (10) is replaced by §163.3184(5), which is new language. The definition of an “affected person” did not change. See the article Process for review and adoption of plan amendments for more.
      4. Compliance Agreements. The language of §163.3184(6)(a), F.S., is new, but borrows heavily from the previous §163.3184(16), F.S., it replaces.
      5. Small scale plan amendments. The provisions of §163.3187, F.S., are changed from directing how all plan amendments are process to just addressing the process for small scale plan amendments. See the article Process for review and adoption of plan amendments for more.
    3. Timing of Implementation. The local government’s comprehensive plan does not have to be amended to implement the new statutory requirements until the next evaluation and appraisal period, unless otherwise specifically required, but all new plan amendments must comply with the new requirements. §163.3161(12), F.S.
    4. Evaluation and appraisal review. The “R” in the “EAR” process now stands for “Review” rather than “Report;” the new EARs process shifts the evaluation and appraisal process from a formal mandated audit report on the comprehensive plan, scrutinized by the state land planning agency, to a less formal review by the local government of whether changes are needed to meet state laws and to reflect the local assessment of needed changes. See the article Evaluation and appraisal review for more.
  • Concurrency. See the article Concurrency for more details.
    1. Premise of concurrency. The premise of concurrency is shifted away from an emphasis on public facilities being available concurrent with development to their being provided so as to achieve and maintain the adopted level of service standards.
    2. Transportation facilities, schools, and parks and recreation. Concurrency for transportation facilities, schools, and parks and recreation is now optional; these facilities are removed as public facilities and services subject to the statutory concurrency requirements on a statewide basis. §163.3180(1), F.S. They may, however, be optionally included in a local government’s concurrency requirements, by the local government’s actions. §163.3180(1), F.S. To rescind any existing concurrency provisions on these now optional concurrency facilities requires a comprehensive plan amendment, but the amendment is not subject to state review. §163.3180(1)(a), F.S.
  • Repeal of rules 9J-5 and 9J-11.023, Florida Administrative Code. The rules of chapter 9J-5 and §9J-11.023, Florida Administrative Code, are repealed and are to be removed from the Florida Administrative Code. §72, 2011-39 Laws of Florida (HB 7207). Some of the rules of chapter 9J-5 have been integrated into the new statute language.
  • Planning Innovations. A new section, §163.3168, F.S., was added to address the concept of innovative planning techniques, which local governments are encouraged to apply. The techniques include addressing future new development areas through visioning, sector planning and rural land stewardship areas and, in urban areas, using urban service area designations, urban growth boundaries, and mixed-use, high density development concepts. §163.3168(2), F.S. See the article Planning Innovations for more details.
  • Sector Plans. The demonstration project “optional sector plan” process of §163.3245, F.S., is now a full scale option to DRI reviews for large acreage (at least 15,000 acres) projects, which can be initiated at the local level, rather than through an agreement with the state land planning agency. See the article Sector Plans for more details.
  • Rural land stewardship areas. Section 163.3248, F.S., is a new section created, in large part, from provisions in previous §163.3177(d).  See the articleRural land stewardship areas for more details.
  • Developments of Regional Impact (DRIs).
    1. DRI thresholds. The DRI “statewide guidelines and standards” thresholds changed for several uses. §380.0651(3), F.S.
    2. Substantial deviation thresholds. The thresholds for when a change to a previously approved DRI will constitute a substantial deviation were changed or deleted for several uses. §380.06(19)(b), F.S.
    3. Date extensions. At the developer’s option, all commencement, phase, buildout, and expiration dates for valid DRIs are extended for four years, regardless of any previous extensions. Associated mitigation requirements may also be extended in many situations. The developer must notify the local government in writing by December 31, 2011 to receive the extension. §380.06(19)(c)2., F.S.
    4. Exemptions from the DRI process.
      1. Two new exemptions were added: new, additions to, or expansions of solid mineral mines, if certain requirements are met, and any development in an energy economic zone designated by §377.809, F.S. §380.06(24)(t) and (w), F.S.
      2. Notwithstanding any agreements that say otherwise, any project no longer subject to DRI review under the revised thresholds is not required to undergo such a review. §380.06(24)(u), F.S.
      3. Significant changes were made to the exemption for dense urban land areas section. §380.06(29), F.S.
  • Referendums prohibited. All initiatives or referendums on a development order or comprehensive plan amendment, not just those affecting five or fewer parcels, are prohibited. §163.3167(8), F.S.
  • Public school interlocal agreements. No new language was added to §163.31777, F.S.; the process was significantly simplified. See the article Public school interlocal agreements” for more details.
  • Local government joint agreements. Section 163.3171(4), F.S., was amended to take the state land planning agency out of the joint agreement process (it cannot enter into joint agreements and is prohibited from interpreting, invalidating or declaring the joint agreements inoperative) and to expand the scope of joint agreements and what they can include.
  • Permit extensions
    1. Any permit or authorization that was extended under section 14 of chapter 2009-96, Laws of Florida (as reauthorized by section 47 of chapter 2010-147, Laws of Florida) is extended and renewed for an additional two year period, for a total of four years, if the holder of the permit notifies the authorizing agency in writing by December 31, 2011. §§ 73(1) and (3), 2011-39 Laws of Florida (HB 7207).
    2. A separate permit extension was provided, “in recognition of 2011 real estate market conditions,” extending “any building permit, and any permit issued by the Department of Environmental Protection or by a water management district pursuant to part IV of chapter 373, Florida Statutes, which has an expiration date from January 1, 2012, through January 1, 2014,” and also “any local government-issued development order or building permit” (including certificates of levels of service), for a period of 2 years after its previously scheduled date of expiration. § 79(1), 2011-39 Laws of Florida (HB 7207). This extension is in addition to any existing permit extension, but cannot exceed four years total. (§ 79(1), 2011-39 Laws of Florida (HB 7207). To get this extension, the holder of such a permit or other authorization must notify the authorizing agency in writing by December 31, 2011. (§ 79(3), 2011-39 Laws of Florida (HB 7207)
    3. There are many provisos and limitations on these extensions. See the article Other, non-statute, provisions of HB 7207 for more details.
Advertisements

Public Schools Interlocal Agreements (§163.31777, F.S.)

This is a summary review of §163.31777, as amended in 2011 (by Section 13 of Florida HB 7207). The review addresses the requirements for public school interlocal agreements.

In this review, the language of the statute may be summarized, paraphrased, re-ordered, and/or reformatted, so refer to the full language of the bill or the official Florida Statutes for the actual statutory provisions. See here, Public schools interlocal agreement, for an unofficial version of the language from the bill integrated into the previous statute provisions.

  1. No new language is added to the section. It is significantly simplified.
    1. The first sentence of previous paragraph 163.31777(1)(a) remains the same – “The county and municipalities located within the geographic area of a school district shall enter into an interlocal agreement with the district school board which jointly establishes the specific ways in which the plans and processes of the district school board and the local governments are to be coordinated.”
    2. A middle sentence of previous paragraph 163.31777(1)(d) – “Local governments and the district school board in each school district are encouraged to adopt a single interlocal agreement to which all join as parties.” – is added to the new subsection (1) to complete that subsection.
    3. The list of items the interlocal agreement must address from previous subsection 163.31777(2), with a simplified introduction sentence, remains the same and comprise the remainder of the section.
  2. The rest of the section is deleted.
    1. The requirement that school interlocal agreements be submitted to the state is eliminated. Accordingly, the submittal schedule and all language related to the state review is deleted. (§163.31777(1), F.S.)
    2. The previous §163.3177(1)(d), F.S., language, addressing interlocal agreements adopted before the adoption of the previous section, is deleted.
    3. The previous §163.3177(5), F.S., language, addressing amendments to public school elements transmitted before the adoption of the previous section, is deleted.
  3. With the removal of the state review from the process, the process for sanctions and other enforcement mechanisms are also eliminated. There does not appear to be any penalty in this section for failure to prepare public school interlocal agreements or failure to prepare the agreement in compliance with the statute requirements.
  4. The administrative proceedings option for affected parties to challenge the consistency of the interlocal agreement with the statutes is eliminated as a separate (and the exclusive) process.

Planning Innovations (§163.3168, F.S.)

This is a summary review of §163.3168, created by Section 8 of Florida 2011 HB 7207. The review addresses the concept of innovative planning. 

In this review, the language of the statute may be summarized, paraphrased, re-ordered, and/or reformatted, so refer to the full language of the bill or the official Florida Statutes for the actual statutory provisions. See here, Planning Innovations, for an unofficial version of the language from the bill.

  1. Local governments are encouraged to apply innovative planning tools. (§163.3168(2), F.S.)
  2. Innovative planning tools include:
    1. To address future new development areas (§163.3168(2), F.S.)
      1. visioning,
      2. sector planning, and
      3. rural land stewardship area designations;
    2. In urban areas (§163.3168(2), F.S.)
      1. urban service area designations,
      2. urban growth boundaries, and
      3. mixed-use, high- density development.
  3. The state land planning agency is tasked with helping communities find creative solutions to fostering vibrant, healthy communities, while protecting the functions of important state resources and facilities. (§163.3168(3), F.S.)
    1. The state land planning agency and all other appropriate state and regional agencies may use various means to provide direct and indirect technical assistance within available resources. (§163.3168(3), F.S.)
    2. If plan amendments may adversely impact important state resources or facilities, upon request by the local government, the state land planning agency shall coordinate multi-agency assistance, if needed, in developing an amendment to minimize impacts on such resources or facilities. (§163.3168(3), F.S.)
    3. The state land planning agency will provide on its website guidance on the submittal and adoption of comprehensive plans, plan amendments, and land development regulations. The “guidance” may not be adopted as a rule and, accordingly, is exempt from §120.54(1)(a). (§163.3168(4), F.S.)

Other, non-statute, changes made by HB 7207

In addition to the many direct changes it makes to the Florida Statutes, HB 7207 makes several other significant changes. These changes include:

  • Repeal of rules 9J-5 and 9J-11.023, Florida Administrative Code
  • Permit extensions
  • Addressing pending administrative or judicial proceedings under statute changes
  • Existing voter referendum comprehensive plan amendments
  • DoT report on calculation of proportionate share contribution
  • House bill 7207 effective date
  1. Rules 9J-5 and 9J-11.023, Florida Administrative Code, are repealed and are to be removed from the Florida Administrative Code. (§ 72, HB 7207)
  2. Permit extensions. See here – Permit Extensions– for the bill language.
    1. Any permit or other authorization that was extended under section 14 of chapter 2009-96, Laws of Florida (as reauthorized by section 47 of chapter 2010-147, Laws of Florida) is extended and renewed for an additional period of 2 years after its previously scheduled expiration date. (§ 73(1), HB 7207)
      1. This extension is in addition to the 2-year permit extension provided under section 14 of chapter 2009-96, Laws of Florida. (§ 73(1), HB 7207)
      2. Permits that were extended by a total of 4 years pursuant to section 14 of chapter 2009-96, Laws of Florida and by section 46 of chapter 2010-147, Laws of Florida, cannot be further extended under this provision. (§ 73(1), HB 7207)
      3. The holder of a valid permit or other authorization that is eligible for the 2-year extension shall notify the authorizing agency in writing by December 31, 2011, identifying the specific authorization for which the holder intends to use the extension and the anticipated timeframe for acting on the authorization. (§ 73(3), HB 7207)

    Continue reading

Concurrency

This is a summary review of §§163.3180 and 163.3182, as amended in 2011 (by Section 15 and 16 of Florida HB 7207). The review addresses the requirements for the concurrency of public facilities.

In this review, the language of the statute may be summarized, paraphrased, re-ordered, and/or reformatted, so refer to the full language of the bills or the official Florida Statutes for the actual statutory provisions. See here, Concurrency provisions, for an unofficial version of the language from the bills integrated into the previous statute provisions.

Section 163.3180, F.S.

  1. The premise of concurrency is shifted away from an emphasis on public facilities being available concurrent with development to their being provided so as to achieve and maintain the adopted level of service standards.
  2. Parks and recreation, schools, and transportation facilities are no longer required to meet concurrency requirements by the State statutes; they are removed as public facilities and services subject to the statutory concurrency requirements on a statewide basis. (§163.3180(1), F.S.)
    1. The parks and recreation facilities standards of previous §163.3180(2)(b) on the timing of the facilities or contributions are deleted.
  3. Parks and recreation, schools, and transportation facilities, and other non-mandatory public facilities, may, however, be included in a local government’s concurrency requirements, by the local government’s actions. (§163.3180(1), F.S.) If the local governments apply concurrency to these other facilities and services, the amended statute provides requirements that must be met. Specifically:

    Continue reading

Requirements for Florida comprehensive plans

This is a summary review of §163.3177, as amended in 2011 (by Section 12 of Florida HB 7207, with one minor amendment by Section 3 of HB 639), with a few relevant provisions from other sections. The review addresses the requirements for local comprehensive plan.

In this review, the language of the statute may be summarized, paraphrased, re-ordered, and/or reformatted, so refer to the full language of the bills or official statutes for the actual statutory provisions. See here, Requirements for Florida comprehensive plans – section 3177 of chapter 163, for an unofficial version of the language from the bills integrated into the previous statute provisions.

  1. This section is extensively rewritten. Much of the new language comes from the repealed provisions of Rule 9J-5, F.A.C.
  2. As with other sections, requirements of detailed monitoring by the state land planning agency are largely deleted. The provisions concerning the state land planning agency rules to implement the statute provisions and the legislative findings relative to these rules, in previous §163.3177(9) and (1), F.S., are deleted.
  3. Local comprehensive plan are still required to include at least two planning periods, one covering at least the first 5-year period occurring after the plan’s adoption and one covering at least a 10-year period. Language has been added to allow additional planning periods for specific components, elements, land use amendments, or projects as part of the planning process. (§163.3177(5)(a), F.S.)
  4. Principles, guidelines, standards, and strategies. The comprehensive plan provides the principles, guidelines, standards, and strategies for the orderly and balanced future economic, social, physical, environmental, and fiscal development of the area that reflects community commitments to implement the plan and its elements. (§163.3177(1), F.S.)
    1. These principles and strategies will guide future decisions in a consistent manner and must contain programs and activities to ensure comprehensive plans are implemented. (§163.3177(1), F.S.)
    2. The format of these principles and guidelines is at the discretion of the local government, but typically is expressed in goals, objectives, policies, and strategies. (§163.3177(1)(c), F.S.)
    3. The sections of the comprehensive plan containing the principles and strategies must describe how the local government’s programs, activities, and land development regulations will be initiated, modified, or continued to implement the comprehensive plan in a consistent manner. (§163.3177(1), F.S.)
  5. The comprehensive plan must identify procedures for monitoring, evaluating, and appraising implementation of the plan. (§163.3177(1)(d), F.S.)
  6. The comprehensive plan and its elements must contain guidelines or policies for the implementation of the plan and its elements. (§163.3177(5)(b), F.S.)
    1. It is not the intent of the statutes, however, to require the inclusion of implementing regulations in the comprehensive plan, but, rather, to require identification of those programs, activities, and land development regulations that will be part of the strategy for implementing the comprehensive plan and the principles that describe how the programs, activities, and land development regulations will be carried out. (§163.3177(1), F.S.)
    2. Accordingly, the plan must establish meaningful and predictable standards for the use and development of land and provide meaningful guidelines for the content of more detailed land development and use regulations. (§163.3177(1), F.S.)
  7. The previous requirements of §163.3177(2) and elsewhere in previous §163.3177, F.S., regarding comprehensive plan financial feasibility, are deleted.
  • Data and analysis. All mandatory and optional elements of the comprehensive plan and plan amendments must be based upon relevant and appropriate data and an analysis by the local government that may include, but not be limited to, surveys, studies, community goals and vision, and other data available at the time of adoption of the comprehensive plan or plan amendment. (§163.3177(1)(f), F.S.)
    1. To be based on data means to react to it in an appropriate way and to the extent necessary indicated by the data available on that particular subject at the time of adoption of the plan or plan amendment at issue. (§163.3177(1)(f), F.S.)
    2. Data must be taken from professionally accepted sources. (§163.3177(1)(f)2., F.S.)
      1. The application of a methodology utilized in data collection or whether a particular methodology is professionally accepted may be evaluated. However, the evaluation may not include whether one accepted methodology is better than another. (§163.3177(1)(f)2., F.S.)
      2. Original data collection by local governments is not required. However, local governments may use original data so long as methodologies are professionally accepted. (§163.3177(1)(f)2., F.S.)
    3. The comprehensive plan must be based upon permanent and seasonal population estimates and projections, which must either be those provided by the University of Florida’s Bureau of Economic and Business Research or generated by the local government based upon a professionally acceptable methodology. (§163.3177(1)(f)3, F.S.)
    4. The plan must be based on at least the minimum amount of land required to accommodate the medium projections of the University of Florida’s Bureau of Economic and Business Research for at least a 10-year planning period unless otherwise limited under s. 380.05, including related rules of the Administration Commission. (§163.3177(1)(f)3, F.S.)
    5. Documents adopted by reference, but not incorporated verbatim into the plan, may be included as part of the adopted plan. The adoption by reference must identify the title and author of the document and indicate clearly what provisions and edition of the document is being adopted. (§163.3177(1)(b), F.S.)
    6. Surveys, studies, and data utilized in the preparation of the comprehensive plan may not be deemed a part of the comprehensive plan unless adopted as a part of it. (§163.3177(1)(f)1., F.S.)
    7. Support data or summaries are not subject to the compliance review process, but the comprehensive plan must be clearly based on appropriate data. Support data or summaries may be used to aid in the determination of compliance and consistency. (§163.3177(1)(f)1., F.S.)
    8. Copies of studies, surveys, data, and supporting documents for proposed plans and plan amendments must be made available for public inspection, and copies of such plans must be made available to the public upon payment of reasonable charges for reproduction. (§163.3177(1)(f)1., F.S.)
  • Coordination of the local comprehensive plan with the comprehensive plans of adjacent municipalities, the county, adjacent counties, or the region; with the appropriate water management district’s regional water supply plans approved pursuant to s. 373.709; and with adopted rules pertaining to designated areas of critical state concern must be a major objective of the local comprehensive planning process. (§163.3177(4)(a), F.S.)
    1. To that end, in the preparation of a comprehensive plan or element, and as adopted, the governing body must include a specific policy statement indicating the relationship of the proposed development of the area to the comprehensive plans of adjacent municipalities, the county, adjacent counties, or the region, as the case may require and as such adopted plans or plans in preparation may exist. (§163.3177(4)(a), F.S.)
    2. When all or a portion of the land in a local government jurisdiction is or becomes part of a designated area of critical state concern, the local government must clearly identify those portions of the local comprehensive plan that will be applicable to the critical area and must indicate the relationship of the proposed development of the area to the rules for the area of critical state concern. (§163.3177(4)(b), F.S.)
  • When a federal, state, or regional agency has implemented a regulatory program, a local government is not required to duplicate or exceed that regulatory program in its local comprehensive plan. (§163.3177(1)(e), F.S.)
    1. Substantially the same language, but addressing a “permitting program” rather than a “regulatory program, is found in §163.3184(4)(d)1., F.S., under the review of plan amendments.
  • Elements, generally.
    1. The comprehensive plan must contain the listed required elements and may include optional elements. (§163.3177(1)(a), F.S.)
      1. The section references “optional elements” in several places, but the optional elements of previous §163.3177(7), F.S., are deleted. It is unclear, but appears that local governments are free to adopt those or other elements at the local government’s discretion, as long as they are consistent with the statutes.
    2. Coordination of the several elements of the local comprehensive plan must be a major objective of the planning process and the elements must be consistent with each other. (§163.3177(2), F.S.)
      1. Where data is relevant to several elements, consistent data must be used, including population estimates and projections, unless alternative data can be justified for a plan amendment through new supporting data and analysis. (§163.3177(2), F.S.)
      2. Each map depicting future conditions must reflect the principles, guidelines, and standards within all elements and each such map must be contained within the comprehensive plan. (§163.3177(2), F.S.)
  • Capital Improvement Element.
    1. The comprehensive plan must contain a capital improvements element designed to consider the need for and the location of public facilities in order to encourage the efficient use of such facilities and set forth: (§163.3177(3)(a), F.S.)
      1. A component that outlines principles for construction, extension, or increase in capacity of public facilities, as well as a component that outlines principles for correcting existing public facility deficiencies, which are necessary to implement the comprehensive plan. The components must cover at least a 5-year period. (§163.3177(3)(a)1., F.S.)
      2. Estimated public facility costs, including a delineation of when facilities will be needed, the general location of the facilities, and projected revenue sources to fund the facilities. (§163.3177(3)(a)2., F.S.)
      3. Standards to ensure the availability of public facilities and the adequacy of those facilities to meet established acceptable levels of service. (§163.3177(3)(a)3., F.S.)
      4. At least in jurisdictions that include transportation concurrency requirements in the comprehensive plan, identification of facilities necessary to meet adopted levels of service during a 5-year period. (§163.3180(5)(d), F.S.)
      5. At least in jurisdictions that include transportation concurrency requirements in the comprehensive plan, a schedule of facilities that are necessary to meet the adopted level of service. (§163.3180(5)(b), F.S.)
      6. A schedule of capital improvements. (§163.3177(3)(a)4., F.S.)
        1. Capital improvements include any publicly funded projects of federal, state, or local government, and may include privately funded projects for which the local government has no fiscal responsibility. (§163.3177(3)(a)4., F.S.)
        2. Projects necessary to ensure that any adopted level-of-service standards are achieved and maintained for the 5-year period must be identified as either funded or unfunded and given a level of priority for funding. (§163.3177(3)(a)4., F.S.)
        3. The schedule must include transportation improvements included in the applicable metropolitan planning organization’s transportation improvement program adopted pursuant to s. 339.175(8) to the extent that such improvements are relied upon to ensure concurrency and financial feasibility. (§163.3177(3)(a)5., F.S.)
        4. The schedule must be coordinated with the applicable metropolitan planning organization’s long-range transportation plan adopted pursuant to s. 339.175(7). (§163.3177(3)(a)5., F.S.)
    2. The capital improvements element must be reviewed by the local government on an annual basis. (§163.3177(3)(b), F.S.)
    3. Modifications to update the 5-year capital improvement schedule may be accomplished by ordinance and is not (and may not be) deemed to be amendments to the local comprehensive plan. (§163.3177(3)(a), F.S.)
    4. Deletions
      1. The previous provision of §163.3177(3)(b)5., F.S., requiring the identification of alternative funding sources for proposed referendum approved funding, is deleted.
      2. The previous requirement of §163.3177(3)(b)1., F.S., that all public facilities must be consistent with the capital improvements element, is deleted.
      3. The provisions of previous §163.3177(3)(c), F.S., concerning the risk of sanctions by the Administration Commission for not meeting obligations identified in the capital improvement element, are deleted.
      4. The provisions relating to requirements of financial feasibility are deleted.
  • Future Land Use Element. The comprehensive plan must include a future land use plan element.
    1. The Future Land Use Element must designate
      1. Proposed future general distribution, location, and extent of the uses of land for:
        1. residential uses,
        2. commercial uses,
        3. industry,
        4. agriculture,
        5. recreation,
        6. conservation,
        7. education,
        8. public facilities, and
        9. other categories of the public and private uses of land. (§163.3177(6)(a), F.S.)
      2. The approximate acreage and the general range of density or intensity of use must be provided for the gross land area included in each existing land use category. (§163.3177(6)(a), F.S.)
      3. Each future land use category must be defined in terms of uses included and must include standards to be followed in the control and distribution of population densities and building and structure intensities. (§163.3177(6)(a)1., F.S.)
      4. The proposed distribution, location, and extent of the various categories of land use must be shown on a land use map or map series which must be supplemented by goals, policies, and measurable objectives. (§163.3177(6)(a)1., F.S.)
    2. The future land use plan element must include criteria to be used to: (§163.3177(6)(a)3., F.S.)
      1. Provide for the compatibility of adjacent land uses.
      2. Achieve the compatibility of lands adjacent or closely proximate to military installations, considering factors identified in s. 163.3175(5).
      3. Achieve the compatibility of lands adjacent to an airport as defined in s. 330.35 and consistent with s. 333.02.
      4. Encourage preservation of recreational and commercial working waterfronts for water dependent uses in coastal communities.
      5. Encourage the location of schools proximate to urban residential areas to the extent possible.
      6. Coordinate future land uses with the topography and soil conditions, and the availability of facilities and services.
      7. Ensure the protection of natural and historic resources.
      8. Provide guidelines for the implementation of mixed use development, including the types of uses allowed, the percentage distribution among the mix of uses, or other standards, and the density and intensity of each use.
    3. The element must establish the long-term end toward which land use programs and activities are ultimately directed. (§163.3177(6)(a), F.S.)
    4. The amount of land designated for future planned uses must provide a balance of uses that foster vibrant, viable communities and economic development opportunities and address outdated development patterns, such as antiquated subdivisions. (§163.3177(6)(a)4., F.S.)
      1. The amount of land designated for future land uses should allow the operation of real estate markets to provide adequate choices for permanent and seasonal residents and business and may not be limited solely by the projected population. (§163.3177(6)(a)4., F.S.)
      2. The element must accommodate at least the minimum amount of land required to accommodate the medium projections of the University of Florida’s Bureau of Economic and Business Research for at least a 10-year planning period unless otherwise limited under s. 380.05, including related rules of the Administration Commission. (§163.3177(6)(a)4., F.S.)
      3. The future land use element must clearly identify the land use categories in which public schools are an allowable use. (§163.3177(6)(a)7., F.S.)
        1. When delineating the land use categories in which public schools are an allowable use, a local government must include in the categories sufficient land proximate to residential development to meet the projected needs for schools in coordination with public school boards and may establish differing criteria for schools of different type or size. (§163.3177(6)(a)7., F.S.)
        2. Each local government must include lands contiguous to existing school sites, to the maximum extent possible, within the land use categories in which public schools are an allowable use. (§163.3177(6)(a)7., F.S.)
    5. The future land use element and any amendment to the future land use element must discourage the proliferation of urban sprawl. (§163.3177(6)(a)9., F.S.)
      1. The proposed comprehensive plan or plan amendment, evaluated in the context of features and characteristics unique to the locality against these primary indicators, does not discourage the proliferation of urban sprawl if the plan or plan amendment: (§163.3177(6)(a)9.a., F.S.)
        1. Promotes, allows, or designates for development substantial areas of the jurisdiction to develop as low-intensity, low-density, or single-use development or uses.
        2. Promotes, allows, or designates significant amounts of urban development to occur in rural areas at substantial distances from existing urban areas while not using undeveloped lands that are available and suitable for development.
        3. Promotes, allows, or designates urban development in radial, strip, isolated, or ribbon patterns generally emanating from existing urban developments.
        4. Fails to adequately protect and conserve natural resources, such as wetlands, floodplains, native vegetation, environmentally sensitive areas, natural groundwater aquifer recharge areas, lakes, rivers, shorelines, beaches, bays, estuarine systems, and other significant natural systems.
        5. Fails to adequately protect adjacent agricultural areas and activities, including silviculture, active agricultural and silvicultural activities, passive agricultural activities, and dormant, unique, and prime farmlands and soils.
        6. Fails to maximize use of existing public facilities and services.
        7. Fails to maximize use of future public facilities and services.
        8. Allows for land use patterns or timing which disproportionately increase the cost in time, money, and energy of providing and maintaining facilities and services, including roads, potable water, sanitary sewer, stormwater management, law enforcement, education, health care, fire and emergency response, and general government.
        9. Fails to provide a clear separation between rural and urban uses.
        10. Discourages or inhibits infill development or the redevelopment of existing neighborhoods and communities.
        11. Fails to encourage a functional mix of uses.
        12. Results in poor accessibility among linked or related land uses.
        13. Results in the loss of significant amounts of functional open space.
      2. The future land use element or plan amendment must be determined to discourage the proliferation of urban sprawl if it incorporates a development pattern or urban form that achieves four or more of the following: (§163.3177(6)(a)9.b., F.S.)
        1. Directs or locates economic growth and associated land development to geographic areas of the community in a manner that does not have an adverse impact on and protects natural resources and ecosystems.
        2. Promotes the efficient and cost-effective provision or extension of public infrastructure and services.
        3. Promotes walkable and connected communities and provides for compact development and a mix of uses at densities and intensities that will support a range of housing choices and a multimodal transportation system, including pedestrian, bicycle, and transit, if available.
        4. Promotes conservation of water and energy.
        5. Preserves agricultural areas and activities, including silviculture, and dormant, unique, and prime farmlands and soils.
        6. Preserves open space and natural lands and provides for public open space and recreation needs.
        7. Creates a balance of land uses based upon demands of residential population for the nonresidential needs of an area.
        8. Provides uses, densities, and intensities of use and urban form that would remediate an existing or planned development pattern in the vicinity that constitutes sprawl or if it provides for an innovative development pattern such as transit-oriented developments or new towns as defined in s. 163.3164.
    6. The future land use plan and plan amendments must be based upon surveys, studies, and data regarding the area, as applicable, including: (§163.3177(6)(a)2., F.S.)
      1. The amount of land required to accommodate anticipated growth.
      2. The projected population of the area.
      3. The character of undeveloped land.
      4. The availability of water supplies, public facilities, and services.
      5. The need for redevelopment, including the renewal of blighted areas and the elimination of nonconforming uses which are inconsistent with the character of the community.
      6. The compatibility of uses on lands adjacent to or closely proximate to military installations.
      7. Lands adjacent to an airport as defined in s. 330.35 and consistent with s. 333.02.
      8. The discouragement of urban sprawl.
      9. The need for job creation, capital investment, and economic development that will strengthen and diversify the community’s economy.
      10. The need to modify land uses and development patterns within antiquated subdivisions.
    7. The future land use plan of a county may designate areas for possible future municipal incorporation. (§163.3177(6)(a)5., F.S.)
    8. The future land use element must include a future land use map or map series. (§163.3177(6)(a)10., F.S.)
      1. The proposed distribution, extent, and location of the following uses must be shown on the future land use map or map series: (§163.3177(6)(a)10.a., F.S.)
        1. Residential.
        2. Commercial.
        3. Industrial.
        4. Agricultural.
        5. Recreational.
        6. Conservation.
        7. Educational.
        8. Public.
      2. The following areas must also be shown on the future land use map or map series, if applicable: (§163.3177(6)(a)10.b., F.S.)
        1. Historic district boundaries and designated historically significant properties meriting protection, generally identified and depicted. (§163.3177(6)(a)6. and 10.b., F.S.)
        2. Transportation concurrency management area boundaries or transportation concurrency exception area boundaries. (§163.3177(6)(a)10.b., F.S.)
        3. Multimodal transportation district boundaries. (§163.3177(6)(a)10.b., F.S.)
        4. Mixed use categories. (§163.3177(6)(a)10.b., F.S.)
      3. The following natural resources or conditions must be shown on the future land use map or map series, if applicable: (§163.3177(6)(a)10.c., F.S.)
        1. Existing and planned public potable waterwells, cones of influence, and wellhead protection areas.
        2. Beaches and shores, including estuarine systems.
        3. Rivers, bays, lakes, floodplains, and harbors.
        4. Wetlands.
        5. Minerals and soils.
        6. Coastal high hazard areas.
    9. Future land use map amendments must be based upon the following analyses: (§163.3177(6)(a)8., F.S.)
      1. An analysis of the availability of facilities and services.
      2. An analysis of the suitability of the plan amendment for its proposed use considering the character of the undeveloped land, soils, topography, natural resources, and historic resources on site.
      3. An analysis of the minimum amount of land needed as determined by the local government. (§163.3177(6)(a)8., F.S.)
    10. Local governments required to update or amend their comprehensive plan to include criteria and address compatibility of lands adjacent or closely proximate to existing military installations, or lands adjacent to an airport as defined in s. 330.35 and consistent with s. 333.02, in their future land use plan element must transmit the update or amendment to the state land planning agency by June 30, 2012. (§163.3177(6)(a)11., F.S.)
  • Transportation Element. The comprehensive plan must include a transportation element that addresses mobility issues in relationship to the size and character of the local government. (§163.3177(6)(b), F.S.)
    1. The purpose of the transportation element is to plan for a multimodal transportation system that places emphasis on public transportation systems, where feasible. (§163.3177(6)(b), F.S.)
    2. The element must provide for a safe, convenient multimodal transportation system, coordinated with the future land use map or map series and designed to support all elements of the comprehensive plan. (§163.3177(6)(b), F.S.)
    3. The element must be coordinated with the plans and programs of any applicable metropolitan planning organization, transportation authority, Florida Transportation Plan, and Department of Transportation’s adopted work program. (§163.3177(6)(b), F.S.)
    4. The element must include a map or map series showing the general location of the existing and proposed transportation system features and be coordinated with the future land use map or map series. (§163.3177(6)(b)1., F.S.)
    5. The element must reflect the data, analysis, and associated principles and strategies relating to: (§163.3177(6)(b)1., F.S.)
      1. The existing transportation system levels of service and system needs and the availability of transportation facilities and services.
      2. The growth trends and travel patterns and interactions between land use and transportation.
      3. Existing and projected intermodal deficiencies and needs.
      4. The projected transportation system levels of service and system needs based upon the future land use map and the projected integrated transportation system.
      5. How the local government will correct existing facility deficiencies, meet the identified needs of the projected transportation system, and advance the purpose of this paragraph and the other elements of the comprehensive plan.
    6. Transportation corridors, as defined in s. 334.03, may be designated in the transportation element pursuant to s. 337.273. (§163.3177(6)(b)1., F.S.)
      1. If the transportation corridors are designated, the local government may adopt a transportation corridor management ordinance. (§163.3177(6)(b)1., F.S.)
    7. Requirements based on relationship to metropolitan planning area.
      1. Local governments that are not located within the metropolitan planning area of an M.P.O. and have a population of 50,000 or less are only required to address transportation circulation. (§163.3177(6)(b), F.S.)
      2. Per the general paragraph, §163.3177(6)(b), F.S., local governments that are not located within the metropolitan planning area of an M.P.O. and have a population of more than 50,000 must address traffic circulation, mass transit, and ports, and aviation and related facilities consistent with this subsection, BUT subparagraph §163.3177(6)(b)3. says that it is municipalities, not all local governments, having populations greater than 50,000 and counties having populations greater than 75,000 that, in addition to traffic circulation, must address mass-transit and plans for port, aviation, and related facilities, as well as plans for the circulation of recreational traffic.
      3. A local government that has all or part of its jurisdiction within the metropolitan planning area of a metropolitan planning organization (M.P.O.), pursuant to §339.175, must prepare and adopt a transportation element addressing the full range of transportation issues, as indicated in §163.3177(6)(b)(2). (§163.3177(6)(b), F.S.)
    8. Traffic circulation. Each local government’s transportation element must address traffic circulation including the types, locations, and extent of existing and proposed major thoroughfares and transportation routes, including bicycle and pedestrian ways. (§163.3177(6)(b)1., F.S.)
    9. Mass transit. The transportation element must include mass-transit provisions addressing:
      1. Proposed methods for the moving of people, rights-of-way, terminals, and related facilities, and
      2. The provision of efficient public transit services based upon existing and proposed major trip generators and attractors, safe and convenient public transit terminals, land uses, and accommodation of the special needs of the transportation disadvantaged. (§163.3177(6)(b)3., F.S.)
    10. Port, aviation, and related facilities. Local governments so required by its size or location (see above) must address in the transportation element port, aviation, and related facilities plans, coordinated with the general circulation and transportation element. (§163.3177(6)(b)3., F.S.)
    11. Recreational traffic. Local governments so required by its size or location (see above) must address in the transportation element plans for the circulation of recreational traffic, including bicycle facilities, exercise trails, riding facilities, and such other matters as may be related to the improvement and safety of movement of all types of recreational traffic. (§163.3177(6)(b)3., F.S.)
    12. Local governments within a metropolitan planning area designated as an M.P.O. pursuant to s. 339.175 must address traffic circulation and: (§163.3177(6)(b)2., F.S.)
      1. All alternative modes of travel, such as public transportation, pedestrian, and bicycle travel.
      2. Aviation, rail, seaport facilities, access to those facilities, and intermodal terminals.
      3. The capability to evacuate the coastal population before an impending natural disaster.
      4. Airports, projected airport and aviation development, and land use compatibility around airports, which includes areas defined in §§ 333.01 and 333.02.
      5. An identification of land use densities, building intensities, and transportation management programs to promote public transportation systems in designated public transportation corridors so as to encourage population densities sufficient to support such systems.
    13. Integration of an airport master plan into the comprehensive plan. (§163.3177(6)(b)4., F.S. – largely from previous §163.3177(6)(k), F.S.)
      1. At the option of the local government, an airport master plan (and any subsequent amendments) prepared by a licensed publicly owned and operated airport under §333.06, may be incorporated into the comprehensive plan of the local government where the airport (or projected airport development) is located, by the adoption of a comprehensive plan amendment. (§163.3177(6)(b)4., F.S.)
      2. The plan amendment that integrates the airport master plan must address:
        1. Land use compatibility, consistent with chapter 333 regarding airport zoning;
        2. The provision of regional transportation facilities for the efficient use and operation of the transportation system and airport;
        3. Consistency with the local government transportation circulation element and applicable M.P.O. long-range transportation plans; and
        4. The execution of any necessary interlocal agreements for the purposes of the provision of public facilities and services to maintain the adopted level-of-service standards for facilities subject to concurrency. (§163.3177(6)(b)4., F.S.)
      3. The integrating plan amendment may address airport-related or aviation-related development. (§163.3177(6)(b)4., F.S.)
      4. Development or expansion of an airport consistent with the adopted airport master plan that has been incorporated into the local comprehensive plan in compliance with this part, and airport-related or aviation-related development that has been addressed in the comprehensive plan amendment that incorporates the airport master plan, do not constitute a development of regional impact.
      5. Notwithstanding any other general law, an airport that has received a development-of-regional-impact development order pursuant to §380.06, but which is no longer required to undergo development-of-regional-impact review pursuant to this subsection, may rescind its development-of-regional-impact order upon written notification to the applicable local government. Upon receipt by the local government, the development-of- regional-impact development order must be deemed rescinded. (§163.3177(6)(b)4., F.S.)
  • General Facilities Element. The comprehensive plan must include a general sanitary sewer, solid waste, drainage, potable water, and natural groundwater aquifer recharge element. (§163.3177(6)(c), F.S.)
    1. The element must be correlated to principles and guidelines for future land use, indicating ways to provide for future potable water, drainage, sanitary sewer, solid waste, and aquifer recharge protection requirements for the area. (§163.3177(6)(c), F.S.)
    2. The element may be a detailed engineering plan, including a topographic map depicting areas of prime groundwater recharge. (§163.3177(6)(c), F.S.)
    3. The element must address in the data and analyses those facilities that provide service within the local government’s jurisdiction. (§163.3177(6)(c)1., F.S.)
      1. Local governments that provide facilities to serve areas within other local government jurisdictions must also address those facilities in the data and analyses, using data from the comprehensive plan for those areas for the purpose of projecting facility needs. (§163.3177(6)(c)1., F.S.)
      2. For shared facilities, each local government must indicate the proportional capacity of the systems allocated to serve its jurisdiction. (§163.3177(6)(c)1., F.S.)
    4. The element must describe the problems and needs, and the general facilities that will be required for solution of the problems and needs, including correcting existing facility deficiencies. (§163.3177(6)(c)2., F.S.)
    5. The element must address coordinating the extension of, or increase in the capacity of, facilities to meet future needs while maximizing the use of existing facilities and discouraging urban sprawl; conservation of potable water resources; and protecting the functions of natural groundwater recharge areas and natural drainage features. (§163.3177(6)(c)2., F.S.)
    6. The element must incorporate, within 18 months after the governing board approves an updated regional water supply plan, the alternative water supply project or projects selected by the local government from those identified in the regional water supply plan pursuant to s. 373.709(2)(a) or proposed by the local government under s. 373.709(8)(b). (§163.3177(6)(c)3., F.S.)
      1. If a local government is located within two water management districts, the local government must adopt its comprehensive plan amendment within 18 months after the later updated regional water supply plan. (§163.3177(6)(c)3., F.S.)
      2. The element must:
        1. Identify such alternative water supply projects and traditional water supply projects and conservation and reuse necessary to meet the water needs identified in s. 373.709(2)(a) within the local government’s jurisdiction; and (§163.3177(6)(c)3., F.S.)
        2. Include a work plan, covering at least a 10-year planning period, for building public, private, and regional water supply facilities, including development of alternative water supplies, which are identified in the element as necessary to serve existing and new development. (§163.3177(6)(c)3., F.S.)
        3. The work plan must be updated, at a minimum, every 5 years within 18 months after the governing board of a water management district approves an updated regional water supply plan. (§163.3177(6)(c)3., F.S.)
      3. Local governments, public and private utilities, regional water supply authorities, special districts, and water management districts are encouraged to cooperatively plan for the development of multijurisdictional water supply facilities that are sufficient to meet projected demands for established planning periods, including the development of alternative water sources to supplement traditional sources of groundwater and surface water supplies. (§163.3177(6)(c)3., F.S.)
  • Conservation Element. The comprehensive plan must include a conservation element.
    1. The element must provide for the conservation, use, and protection of area natural resources, including factors affecting energy conservation. (§163.3177(6)(d), F.S.)
      1. The list of the natural resources to be addressed include air, water, water recharge areas, wetlands, water wells, estuarine marshes, soils, beaches, shores, flood plains, rivers, bays, lakes, harbors, forests, fisheries and wildlife, marine habitat, minerals, and other natural and environmental resources. (§163.3177(6)(d), F.S.)
    2. The following natural resources, where present within the local government’s boundaries, must be identified and analyzed and existing recreational or conservation uses, known pollution problems, including hazardous wastes, and the potential for conservation, recreation, use, or protection must also be identified: (§163.3177(6)(d)1., F.S.)
      1. Rivers, bays, lakes, wetlands including estuarine marshes, groundwaters, and springs, including information on quality of the resource available.
      2. Floodplains.
      3. Known sources of commercially valuable minerals.
      4. Areas known to have experienced soil erosion problems.
      5. Areas that are the location of recreationally and commercially important fish or shellfish, wildlife, marine habitats, and vegetative communities (including forests), indicating known dominant species present and species listed by federal, state, or local government agencies as endangered, threatened, or species of special concern.
    3. The element must contain principles, guidelines, and standards for conservation that provide long-term goals and which: (§163.3177(6)(d)2., F.S.)
      1. Protects air quality.
      2. Conserves, appropriately uses, and protects the quality and quantity of current and projected water sources and waters that flow into estuarine waters or oceanic waters.
      3. Protects from activities and land uses known to affect adversely the quality and quantity of identified water sources, including natural groundwater recharge areas, wellhead protection areas, and surface waters used as a source of public water supply.
      4. Provides for the emergency conservation of water sources in accordance with the plans of the regional water management district.
      5. Conserves, appropriately uses, and protects minerals, soils, and native vegetative communities, including forests, from destruction by development activities.
      6. Conserves, appropriately uses, and protects fisheries, wildlife, wildlife habitat, and marine habitat.
      7. Restricts activities known to adversely affect the survival of endangered and threatened wildlife.
      8. Protects existing natural reservations identified in the recreation and open space element.
      9. Maintains cooperation with adjacent local governments to conserve, appropriately use, or protect unique vegetative communities located within more than one local jurisdiction.
      10. Designates environmentally sensitive lands for protection based on locally determined criteria which further the goals and objectives of the conservation element.
      11. Manages hazardous waste to protect natural resources.
      12. Protects and conserves wetlands and the natural functions of wetlands.
      13. Directs future land uses that are incompatible with the protection and conservation of wetlands and wetland functions away from wetlands. (§163.3177(6)(d)2., F.S.)
        1. The type, intensity or density, extent, distribution, and location of allowable land uses and the types, values, functions, sizes, conditions, and locations of wetlands are land use factors that must be considered when directing incompatible land uses away from wetlands.
        2. Land uses must be distributed in a manner that minimizes the effect and impact on wetlands.
        3. The protection and conservation of wetlands by the direction of incompatible land uses away from wetlands must occur in combination with other principles, guidelines, standards, and strategies in the comprehensive plan.
        4. Where incompatible land uses are allowed to occur, mitigation must be considered as one means to compensate for loss of wetlands functions.
    4. The element must analyze current and projected needs and sources, for at least a 10-year period, based on the demands for industrial, agricultural, and potable water use and the quality and quantity of water available to meet these demands. (§163.3177(6)(d)3., F.S.)
      1. The analysis must consider the existing levels of water conservation, use, and protection and applicable policies of the regional water management district. (§163.3177(6)(d)3., F.S.)
      2. The analysis must also consider the appropriate regional water supply plan approved pursuant to s. 373.709, or, in the absence of an approved regional water supply plan, the district water management plan approved pursuant to s. 373.036(2). (§163.3177(6)(d)3., F.S.)
      3. This information must be submitted to the appropriate agencies. (§163.3177(6)(d)3., F.S.)
  • Recreation and Open Space Element. The comprehensive plan must include a recreation and open space element indicating a comprehensive system of public and private sites for recreation, including, but not limited to, natural reservations, parks and playgrounds, parkways, beaches and public access to beaches, open spaces, waterways, and other recreational facilities. (§163.3177(6)(e), F.S.)
  • Housing Element. The comprehensive plan must include a housing element. (§163.3177(6)(f), F.S.)
    1. The housing element must contain principles, guidelines, standards, and strategies to be followed in: (§163.3177(6)(f)1., F.S.)
      1. The provision of housing for all current and anticipated future residents of the jurisdiction.
      2. The elimination of substandard dwelling conditions.
      3. The structural and aesthetic improvement of existing housing.
      4. The provision of adequate sites for future housing, including affordable workforce housing as defined in s. 380.0651(3)(h), housing for low-income, very low-income, and moderate-income families, mobile homes, and group home facilities and foster care facilities, with supporting infrastructure and public facilities.
      5. Provision for relocation housing and identification of historically significant and other housing for purposes of conservation, rehabilitation, or replacement.
      6. The formulation of housing implementation programs.
      7. The creation or preservation of affordable housing to minimize the need for additional local services and avoid the concentration of affordable housing units only in specific areas of the jurisdiction.
      8. The previous references requiring consideration of energy efficiency and the use of renewable energy resources are deleted.
      9. The requirement of a separate affordable workforce housing plan in certain counties of previous §163.3177(6)(f)1.j., F.S., is deleted.
    2. The element may include provisions that specifically address affordable housing for persons 60 years of age or older. Real property that is conveyed to a local government for affordable housing under this sub-subparagraph must be disposed of by the local government pursuant to s. 125.379 or s. 166.0451. (§163.3177(6)(f)1.d., F.S.) [added by 2011-HB639]
    3. The guidelines, standards, and strategies must reflect, as needed: (§163.3177(6)(f)3., F.S.)
      1. the creation and preservation of affordable housing for all current and anticipated future residents of the jurisdiction,
      2. elimination of substandard housing conditions,
      3. adequate sites, and
      4. distribution of housing for a range of incomes and types, including mobile and manufactured homes.
    4. The element must provide for specific programs and actions to partner with private and nonprofit sectors to address housing needs in the jurisdiction, streamline the permitting process, and minimize costs and delays for affordable housing, establish standards to address the quality of housing, stabilization of neighborhoods, and identification and improvement of historically significant housing. (§163.3177(6)(f)3., F.S.)
    5. Data and analysis.
      1. The principles, guidelines, standards, and strategies of the housing element must be based on the data and analysis prepared on housing needs, including an inventory taken from the latest decennial United States Census or more recent estimates. (§163.3177(6)(f)2., F.S.)
      2. The data and analysis/inventory must include the number and distribution of dwelling units by type, tenure, age, rent, value, monthly cost of owner-occupied units, and rent or cost to income ratio, and must show the number of dwelling units that are substandard. (§163.3177(6)(f)2., F.S.)
      3. The inventory must also include the methodology used to estimate the condition of housing, a projection of the anticipated number of households by size, income range, and age of residents derived from the population projections, and the minimum housing need of the current and anticipated future residents of the jurisdiction. (§163.3177(6)(f)2., F.S.)
    6. State and federal housing plans prepared on behalf of the local government must be consistent with the goals, objectives, and policies of the housing element. (§163.3177(6)(f)4., F.S.)
    7. Local governments are encouraged to use job training, job creation, and economic solutions to address a portion of their affordable housing concerns. (§163.3177(6)(f)4., F.S.)
    8. The provisions of previous §163.3177(6)(f)2., addressing state conducted affordable housing needs assessments, are deleted.
  • Coastal Management Element. The comprehensive plan in those local governments identified in §380.24 (which did not change) must include a coastal management element. (§163.3177(6)(g), F.S.)
    1. The element must be appropriately related to its conservation element and recreation and open space element. (§163.3177(6)(g), F.S.)
    2. The coastal management element must set forth the principles, guidelines, standards, and strategies that will guide the local government’s decisions and program implementation with respect to the following objectives: (§163.3177(6)(g), F.S.)
      1. Maintain, restore, and enhance the overall quality of the coastal zone environment, including, but not limited to, its amenities and aesthetic values.
      2. Preserve the continued existence of viable populations of all species of wildlife and marine life.
      3. Protect the orderly and balanced utilization and preservation, consistent with sound conservation principles, of all living and nonliving coastal zone resources.
      4. Avoid irreversible and irretrievable loss of coastal zone resources.
      5. Use ecological planning principles and assumptions in the determination of the suitability permitted development.
      6. Limit public expenditures that subsidize development in coastal high-hazard areas.
      7. Protect human life against the effects of natural disasters.
      8. Direct the orderly development, maintenance, and use of ports identified in s. 403.021(9) to facilitate deepwater commercial navigation and other related activities.
      9. Preserve historic and archaeological resources, which include the sensitive adaptive use of these resources.
    3. At the option of the local government, the coastal management element may include an adaptation action area designation for those low-lying coastal zones that are experiencing coastal flooding due to extreme high tides and storm surge and are vulnerable to the impacts of rising sea level. (§163.3177(6)(g)10., F.S.)
      1. Local governments that adopt an adaptation action area may consider policies within the coastal management element to improve resilience to coastal flooding resulting from high-tide events, storm surge, flash floods, stormwater runoff, and related impacts of sea level rise. (§163.3177(6)(g)10., F.S.)
      2. Criteria for the adaptation action area may include, but need not be limited to, areas for which the land elevations are below, at, or near mean higher high water, which have a hydrologic connection to coastal waters, or which are designated as evacuation zones for storm surge. (§163.3177(6)(g)10., F.S.)
    4. The element must meet the requirements of §163.3178(2), (§163.3177(6)(g), F.S.), which says the element must:
      1. Be based on studies, surveys, and data; (§163.3178(2), F.S.)
      2. Be consistent with coastal resource plans prepared and adopted pursuant to general or special law; and (§163.3178(2), F.S.)
      3. Contain: (§163.3178(2), F.S.)
        1. A land use and inventory map of existing coastal uses, wildlife habitat, wetland and other vegetative communities, undeveloped areas, areas subject to coastal flooding, public access routes to beach and shore resources, historic preservation areas, and other areas of special concern to local government.
        2. An analysis of the environmental, socioeconomic, and fiscal impact of development and redevelopment proposed in the future land use plan, with required infrastructure to support this development or redevelopment, on the natural and historical resources of the coast and the plans and principles to be used to control development and redevelopment to eliminate or mitigate the adverse impacts on coastal wetlands; living marine resources; barrier islands, including beach and dune systems; unique wildlife habitat; historical and archaeological sites; and other fragile coastal resources.
        3. An analysis of the effects of existing drainage systems and the impact of point source and nonpoint source pollution on estuarine water quality and the plans and principles, including existing state and regional regulatory programs, which must be used to maintain or upgrade water quality while maintaining sufficient quantities of water flow.
        4. A component which outlines principles for hazard mitigation and protection of human life against the effects of natural disaster, including population evacuation, which take into consideration the capability to safely evacuate the density of coastal population proposed in the future land use plan element in the event of an impending natural disaster. The Division of Emergency Management must manage the update of the regional hurricane evacuation studies, ensure such studies are done in a consistent manner, and ensure that the methodology used for modeling storm surge is that used by the National Hurricane Center.
        5. A component which outlines principles for protecting existing beach and dune systems from human-induced erosion and for restoring altered beach and dune systems.
        6. A redevelopment component which outlines the principles which must be used to eliminate inappropriate and unsafe development in the coastal areas when opportunities arise.
        7. A shoreline use component that identifies public access to beach and shoreline areas and addresses the need for water-dependent and water-related facilities, including marinas, along shoreline areas. Such component must include the strategies that will be used to preserve recreational and commercial working waterfronts as defined in s. 342.07.
        8. Designation of coastal high-hazard areas and the criteria for mitigation for a comprehensive plan amendment in a coastal high-hazard area as defined in subsection 163.3178(9), F.S. The coastal high-hazard area is the area below the elevation of the category 1 storm surge line as established by a Sea, Lake, and Overland Surges from Hurricanes (SLOSH) computerized storm surge model. Application of mitigation and the application of development and redevelopment policies, pursuant to s. 380.27(2), and any rules adopted thereunder, must be at the discretion of local government.
        9. A component which outlines principles for providing that financial assurances are made that required public facilities will be in place to meet the demand imposed by the completed development or redevelopment. Such public facilities will be scheduled for phased completion to coincide with demands generated by the development or redevelopment.
        10. An identification of regulatory and management techniques that the local government plans to adopt or has adopted in order to mitigate the threat to human life and to control proposed development and redevelopment in order to protect the coastal environment and give consideration to cumulative impacts.
        11. A component which includes the comprehensive master plan prepared by each deepwater port listed in s. 311.09(1), which addresses existing port facilities and any proposed expansions, and which adequately addresses the applicable requirements of paragraphs (a)-(k) for areas within the port and proposed expansion areas. Such component must be submitted to the appropriate local government at least 6 months prior to the due date of the local plan and must be integrated with, and must meet all criteria specified in, the coastal management element. “The appropriate local government” means the municipality having the responsibility for the area in which the deepwater port lies, except that where no municipality has responsibility, where a municipality and a county each have responsibility, or where two or more municipalities each have responsibility for the area in which the deepwater port lies, “the appropriate local government” means the county which has responsibility for the area in which the deepwater port lies. Failure by a deepwater port which is not part of a local government to submit its component to the appropriate local government must not result in a local government being subject to sanctions pursuant to ss. 163.3167 and 163.3184. However, a deepwater port which is not part of a local government must be subject to sanctions pursuant to s. 163.3184.
    5. The element must meet the requirements of §163.3178(3). (§163.3177(6)(g), F.S.)
    6. The provisions of previous §163.3177(6)(g)2., F.S., addressing recreational surface water use policies, are deleted.
  • Intergovernmental Coordination Element. The comprehensive plan must include a intergovernmental coordination element. (§163.3177(6)(h)1., F.S.)
    1. The element must show relationships and state principles and guidelines to be used in coordinating the adopted comprehensive plan: (§163.3177(6)(h)1., F.S.)
      1. with the plans of: (§163.3177(6)(h)1. and 2., F.S.)
        1. school boards,
        2. regional water supply authorities, and
        3. other units of local government providing services, but not having regulatory authority over the use of land,
      2. with the comprehensive plans of:
        1. adjacent municipalities,
        2. the county,
        3. adjacent counties, or
        4. the region,
      3. with the state comprehensive plan and
      4. with the applicable regional water supply plan,
      5. as the case may require and as such adopted plans or plans in preparation may exist.
    2. The element must:
      1. Demonstrate consideration of the particular effects of the adopted local plan on the development of adjacent municipalities, the county, adjacent counties, or the region, or upon the state comprehensive plan, as the case may require. (§163.3177(6)(h)1., F.S.)
      2. Ensure that the local government addresses, through coordination mechanisms, the impacts of development proposed in the local comprehensive plan upon development in adjacent municipalities, the county, adjacent counties, the region, and the state. (§163.3177(6)(h)3.a., F.S.)
        1. The area of concern for municipalities must include adjacent municipalities, the county, and counties adjacent to the municipality. (§163.3177(6)(h)(3)a., F.S.)
        2. The area of concern for counties must include all municipalities within the county, adjacent counties, and adjacent municipalities. (§163.3177(6)(h)3.a., F.S.)
      3. Provide procedures for identifying and implementing joint planning areas, especially for the purpose of annexation, municipal incorporation, and joint infrastructure service areas. (§163.3177(6)(h)1.a., F.S.)
      4. Provide for a dispute resolution process, as established pursuant to s. 186.509, for bringing intergovernmental disputes to closure in a timely manner. (§163.3177(6)(h)1.b., F.S.)
      5. Provide for interlocal agreements as established pursuant to s. 333.03(1)(b). (§163.3177(6)(h)1.c., F.S.)
      6. Describe joint processes for collaborative planning and decision-making on population projections and public school siting, the location and extension of public facilities subject to concurrency, and siting facilities with countywide significance, including locally unwanted land uses whose nature and identity are established in an agreement. (§163.3177(6)(h)2., F.S.)
      7. Ensure coordination in establishing level of service standards for public facilities with any state, regional, or local entity having operational and maintenance responsibility for such facilities. (§163.3177(6)(h)3.b., F.S.)
    3. Within 1 year after adopting their intergovernmental coordination elements, each county, all the municipalities within that county, the district school board, and any unit of local government service providers in that county must establish, by interlocal agreement or other formal agreement executed by all affected entities, the joint processes described in the statute consistent with their adopted intergovernmental coordination elements. (§163.3177(6)(h)3., F.S.)
    4. Deletions
      1. The requirement that the intergovernmental coordination element recognize campus master plans and airport master plans of previous §163.3177(6)(h)1.b., F.S., is deleted.
      2. The provisions of former §163.3177(6)(h)5.-7, concerning a report to the Department of Community Affairs on service deficiencies, are deleted.
  • The provisions addressing public school facilities elements in former §163.3177(12), F.S., are deleted.
  • The provisions defining consistency, as it relates to consistency of local comprehensive plans with the state comprehensive plan and appropriate regional policy plan, in former §163.3177(10)(a), F.S., are deleted. This deletion, coupled with the deletion of chapter 9J-5, F.A.C., eliminates the explicit definitions of the “compatible with” and “furthers” terms that are used in the “consistency” provision of §163.3194(3)(a), F.S., which was not deleted. See the updated Consistency with the comprehensive plan for more on the definition of consistency.
  • The provisions in former §163.3177(10), F.S., addressing the rules of chapter 9J-5, are deleted.
  • The community vision provisions of former §163.3177(13), F.S., are deleted.
  • The urban service boundary provisions of former §163.3177(14), F.S., are deleted.

Process for review and adoption of plan amendments (§§163.3184 and 163.3187, F.S.)

This is a summary review of §§163.3184 and 163.3187, F.S., as amended in 2011 (by Sections 17 and 18 of Florida HB 7207). It addresses the process of amending the local comprehensive plan.

In this review, the language of the statute may be summarized, paraphrased, re-ordered, and/or reformatted, so refer to the full language of the bill or the official Florida Statutes for the actual statutory provisions.

  1. Section 163.3184 is changed to direct how all plan amendments, except small-scale amendments, are processed. Section 163.3187 is changed from directing how all plan amendments are processed to just addressing the process for small-scale amendments.
  2. A significant change is the deletion of the restriction limiting amendments of the comprehensive plan to no more than twice a year, from previous §163.3187(1)(a), F.S.
  3. The definition of “in compliance” is amended to remove the reference to the state comprehensive plan and chapter 9J-5, Florida Administrative Code. (§163.3184(1)(b), F.S.)
  4. A definition list of “reviewing agencies” is added. (§163.3184(1)(c), F.S.)
  5. Expedited State Review Process. An expedited state review process, based on the previous §163.32465(2) pilot program, is added.
    1. All plan amendments, on a state-wide basis, must follow this expedited process except: in an area of critical state concern, that propose a rural land stewardship area or a sector plan, that update the comprehensive plan based on a § 163.3191 evaluation and appraisal, or that are for a new plan for a newly incorporated municipality. The exceptions must follow the “State coordinated review process” of §163.3184(4). (§163.3184(2) and (3)(a), F.S.)
    2. Qualifying small-scale development amendments may use the expedited process or the small scale process of §163.3187. (§163.3184(2)(b), F.S.)
    3. Reviewers’ commenting process (all new language, although some is borrowed).
      1. Within 10 days of the initial public hearing, the local government must transmit the proposed amendments, and appropriate supporting data and analyses, to the applicable “reviewing agencies” and any other local government or governmental agency that has filed a written request (“reviewers” for this discussion). (§163.3184(3)(b)1., F.S.)
      2. The reviewers must transmit their comments so they are received by the local government not later than 30 days from the date the reviewer received the plan amendment and must also send a copy of their comments to the state land planning agency. (§163.3184(3)(b)2., F.S.)
      3. The reviewers are limited in the allowable scope of their comments.
        1. State agencies may only comment on important state resources and facilities that would be adversely impacted by the amendment and must state their comments with specificity, identifying measures the local government may take to eliminate, reduce, or mitigate the adverse impacts. Such state agency comments, if not resolved, may result in a challenge by the state land planning agency to the plan amendment. (§163.3184(3)(b)2., F.S.)
      4. The Department of Environmental Protection must limit its comments to the subjects of air and water pollution; wetlands and other surface waters of the state; federal and state-owned lands and interests in lands; solid waste; water and wastewater treatment; and the Everglades ecosystem restoration. (§163.3184(3)(b)4.a., F.S.)
      5. The Department of State must limit its comments to the subjects of historic and archeological resources. (§163.3184(3)(b)4.b., F.S.)
      6. The Department of Transportation must limit its comments to issues within the agency’s jurisdiction related to transportation resources and facilities of state importance. (§163.3184(3)(b)4.c., F.S.)
      7. The Fish and Wildlife Conservation Commission must limit its comments to subjects relating to fish and wildlife habitat and listed species and their habitat. (§163.3184(3)(b)4.d., F.S.)
      8. The Department of Agriculture and Consumer Services must limit its comments to the subjects of agriculture, forestry, and aquaculture issues. (§163.3184(3)(b)4.e., F.S.)
      9. The Department of Education must limit its comments to the subject of public school facilities. (§163.3184(3)(b)4.f., F.S.)
      10. The appropriate water management district must limit its comments to flood protection and floodplain management, wetlands and other surface waters, and regional water supply. (§163.3184(3)(b)4.g., F.S.)
      11. The state land planning agency must limit its comments to important state resources and facilities outside the jurisdiction of other commenting state agencies and may include comments on countervailing planning policies and objectives served by the plan amendment that should be balanced against potential adverse impacts to important state resources and facilities.(§163.3184(3)(b)4.h., F.S.)
      12. The regional planning council comments are limited to adverse effects on regional resources or facilities identified in the strategic regional policy plan and extra-jurisdictional impacts that would be inconsistent with the comprehensive plan of any affected local government within the region. A regional planning council may not comment on a proposed plan amendment prepared by the council unless the plan amendment has been changed by the local government after it was prepared by the regional planning council. (§163.3184(3)(b)3.a., F.S.)
      13. County comments must be in the context of the relationship and effect of the proposed plan amendments on the county plan. (§163.3184(3)(b)3.b., F.S.)
      14. Municipal comments must be in the context of the relationship and effect of the proposed plan amendments on the municipal plan. (§163.3184(3)(b)3.c., F.S.)
      15. Military installation comments must follow §163.3175. (§163.3184(3)(b)3.d., F.S.)
  6. The second public hearing, which is the hearing on whether or not to adopt the plan amendment, is held in the same manner as the non-expedited review second public hearing. (§163.3184(3)(c)1., F.S.)
  7. If the local government fails to hold the second public hearing on the plan amendments, except those processed pursuant to §380.06, within 180 days after the receipt of the reviewers’ comments, the amendments must be deemed withdrawn, unless extended by agreement (the statute does not say between whom) with notice to the state land planning agency and any “affected person” who provided comments on the amendment. (§163.3184(3)(c)1., F.S.)
  8. An adopted plan amendment, along with the supporting data and analysis, must be transmitted within 10 days after the second public hearing to the state land planning agency and any timely commenting reviewers. (§163.3184(3)(c)2., F.S.)
    1. The transmitted amendment package must be “complete.” To be complete, an amendment must contain:
      1. a full, executed copy of the adoption ordinance;
      2. in the case of a text amendment, a full copy of the amended language in legislative format with new words inserted in the text underlined, and words deleted stricken with hyphens;
      3. in the case of a future land use map amendment, a copy of the future land use map clearly depicting the parcel, its existing future land use designation, and its adopted designation; and
      4. a copy of any data and analyses the local government deems appropriate. (§163.3184(3)(c)3., F.S.)
  9. The state land planning agency must notify the local government of any deficiencies within five working days after the receipt of a complete amendment package. (§163.3184(3)(c)3., F.S.)
  10. An amendment adopted under this process that is not challenged, in a timely manner, becomes effective 31 days after the state land planning agency notifies the local government that the plan amendment package is complete. (§163.3184(3)(c)4., F.S.)
  11. If timely challenged, an amendment does not become effective until the state land planning agency or the Administration Commission enters a final order determining the adopted amendment to be in compliance. (§163.3184(3)(c)4., F.S.)
  • State Coordinated Review Process.
    1. All comprehensive plans or plan amendments that aren’t reviewed under the expedited or small-scale review process are reviewed through this process. (§163.3184(4)(a), F.S.)
    2. The state land planning agency is responsible for plan review, coordination, and the preparation and transmission of comments to the local government for this type of review. (§163.3184(4)(a), F.S.)
    3. Local government transmittal. Immediately following the first public hearing on a comprehensive plan or plan amendment under this process, the local government must transmit the plan amendment, clearly identified as being under this type of review, to the “reviewing agencies” and any other unit of local government or government agency in the state that has so requested by written request. (§163.3184(4)(b), F.S.)
      1. The previous language of §163.3184(3)(b), F.S., about what materials should be sent to what agency, is deleted.
      2. The previous language of §163.3184(3)(d), F.S., about what constitutes an amendment cycle, is deleted.
    4. Reviewers’ comments. The reviewing agencies comments and any other commenter (except the state land planning agency) are to be made in the same manner and with the same restrictions as for the expedited state review process except any comments must be sent by the agencies to the state land planning agency within 30 days after the state land planning agency received the complete proposed plan or plan amendment from the local government. (§163.3184(4)(c), F.S.)
      1. The previous language of §163.3184(5), F.S., about the review by the regional planning council, any county, or any municipality, is deleted, as that was indicated (in substantially similar language) in the expedited review process and applied by reference.
    5. Written comments submitted by the public are to be sent directly to the local government. (§163.3184(4)(c), F.S.)
    6. The state land planning agency review.
      1. If the state land planning agency elects to review a plan or plan amendment submitted through this process, the agency must issue a report giving its objections, recommendations, and comments (“ORC report”) within 60 days after the receipt of the plan or plan amendment. (§163.3184(4)(d)1., F.S.)
      2. Notwithstanding the limitations on comments by the state land planning agency indicated in the expedited process, the state land planning agency may make objections, recommendations, and comments in its report regarding whether the plan or plan amendment is in compliance and/or will adversely impact important state resources and facilities. (§163.3184(4)(d)1., F.S.)
        1. Although the enrolled version of the adopting bill indicates sub-subparagraph (3)(b)4.g., it is assumed the reference was supposed to be to (3)(b)4.h. instead, since that is the one that speaks to the state land planning agency comment limitations.
      3. The state land planning agency, in conducting its review of local plans or plan amendments, may make objections, recommendations, and comments regarding densities and intensities consistent with the provisions of the statute. (§163.3184(4)(d)1., F.S.)
      4. Any objection that says the plan or plan amendment will adversely impact an important state resource or facility must specify how the important state resource or facility will be impacted and identify measures the local government may take to eliminate, reduce, or mitigate the adverse impacts. (§163.3184(4)(d)1., F.S.)
      5. In preparing its comments, the state land planning agency must only base its considerations on written, and not oral, comments. (§163.3184(4)(d)1., F.S.)
      6. The state land planning agency review must identify all written communications with the agency regarding the proposed plan amendment. The written identification must include a list of all documents received or generated by the agency, which list must be of sufficient specificity to enable the documents to be identified and copies requested, if desired, and the name of the person to be contacted to request copies of any identified document. (§163.3184(4)(d)2., F.S.)
      7. The previous language of §163.3184(6)(a), F.S., about the review by the state land planning agency at the request of a regional planning council, affected person, or local government, is deleted
      8. The previous language of §163.3184(6)(b), F.S., about the state land planning agency being able to review any proposed plan amendment if notice is provided to the local government, is deleted
    7. When a federal, state, or regional agency has implemented a permitting program, a local government is not required to duplicate or exceed that permitting program in its comprehensive plan or to implement such a permitting program in its land development regulations. (§163.3184(4)(d)1., F.S.)
      1. The presence of substantially the same language in §163.3177(1)(e), F.S., which addresses the requirements of comprehensive plans, indicates this provision has wider application than just the state land planning agency review of plan amendments.
    8. Local government review of comments. The local government must review the report submitted to it by the state land planning agency, if any, and any written comments submitted to it by any other person, agency, or government. (§163.3184(4)(e)1., F.S.)
    9. Adoption of the comprehensive plan or plan amendment. Upon receipt of the report from the state land planning agency, the local government must hold the decision public hearing, to adopt or not adopt the plan or plan amendment, pursuant to the provisions of subsection 163.3184(11). Except plan amendments processed pursuant to the DRI process, if the hearing is not held within 180 days after receipt of the state land planning agency’s report, the amendments will be deemed withdrawn, unless extended by agreement (between the applicant and the local government?) with notice to the state land planning agency and any “affected person” that provided comments. (§163.3184(4)(e)1., F.S.)
    10. Transmittal.
      1. All comprehensive plan amendments adopted by the governing body, along with the supporting data and analysis, must be transmitted within 10 days after the second public hearing to the state land planning agency and any other agency or local government that provided timely comments. (§163.3184(4)(e)2., F.S.)
      2. The state land planning agency must notify the local government of any completeness deficiencies within 5 working days after receipt of a plan or plan amendment package. What constitutes a “complete” package is the same as required for the expedited review process. (§163.3184(4)(e)3., F.S.)
    11. After the state land planning agency makes a completeness determination, the agency has 45 days to determine if the plan or plan amendment is in compliance with the Community Planning Act. (§163.3184(4)(e)4., F.S.)
      1. Unless the plan or plan amendment is substantially changed from the one commented on, the state land planning agency’s compliance determination is limited to objections raised in the “ORC” report. (§163.3184(4)(e)4., F.S.)
      2. Within the 45 day determination period, a senior administrator or the secretary of the state land planning agency must issue a notice of intent to find that the plan or plan amendment is or is not in compliance. (§163.3184(4)(e)4., F.S.)
      3. A copy of the notice of intent must be posted on the state land planning agency’s Internet website. This publication of the notice of intent on the state land planning agency’s Internet site is prima facie evidence of compliance with the publication requirements. (§163.3184(4)(e)4., F.S.)
    12. Effective date.
      1. A plan or plan amendment adopted under the state coordinated review process goes into effect pursuant to the state land planning agency’s notice of intent. (§163.3184(4)(e)5., F.S.)
      2. If timely challenged, an amendment does not become effective until the state land planning agency or the Administration Commission enters a final order determining the adopted amendment to be in compliance. (§163.3184(4)(e)5., F.S.)

  • Administrative challenges to comprehensive plans and plan amendments. (all new language)
    1. This process replaces the provisions of §163.3184(9) and (10)
    2. Any “affected person” (the definition of which did not change) may file a petition with the Division of Administrative Hearing, pursuant to ss. 120.569 and 120.57, with a copy served on the affected local government, within 30 days after the local government adopts the plan or amendment, to request a formal hearing to challenge whether the plan or plan amendments are “in compliance,” as defined in the section. (§163.3184(5)(a), F.S.)
      1. The state land planning agency may not intervene in this proceeding. (§163.3184(5)(a), F.S.)
      2. Due to the timing deadlines, an affected person wishing to file may not know the state land planning agency’s decision on whether the amendment is in compliance before the filing deadline.
    3. The state land planning agency may file a petition with the Division of Administrative Hearings, pursuant to ss. 120.569 and 120.57, with a copy served on the affected local government, to request a formal hearing to challenge whether the plan or plan amendments are “in compliance,” as defined in the section. (§163.3184(5)(b), F.S.)
      1. The agency’s petition must clearly state the reasons for the challenge.
      2. Under the expedited state review process, the petition must be filed with the division within 30 days after the state land planning agency notifies the local government the plan amendment package is “complete.” (§163.3184(5)(b), F.S.)
      3. Under the state coordinated review process, the petition filing deadline is 45 days after the state land planning agency notifies the local government that the plan amendment package is “complete.” (§163.3184(5)(b), F.S.)
      4. The agency’s challenge to a plan amendment adopted under the expedited state review process is limited to the comments provided by the reviewing agencies, upon a determination by the state land planning agency that an important state resource or facility will be adversely impacted by the adopted plan amendment. (§163.3184(5)(b)1., F.S.)
        1. The petition must state with specificity how the plan amendment will adversely impact the important state resource or facility. (§163.3184(5)(b)1., F.S.)
        2. The agency may challenge a plan amendment that has substantially changed from the version on which the agencies commented but only upon a determination by the state land planning agency that an important state resource or facility will be adversely impacted. (§163.3184(5)(b)1., F.S.)
    4. If the state land planning agency issues a notice of intent to find the comprehensive plan or plan amendment not in compliance with this act, the notice of intent must be forwarded to the Division of Administrative Hearings, which will conduct a proceeding under ss. 120.569 and 120.57 in the county of and convenient to the affected local jurisdiction. (§163.3184(5)(b)2., F.S.)
      1. The parties to the proceeding will be the state land planning agency, the affected local government, and any affected person who intervenes. (§163.3184(5)(b)2., F.S.)
      2. No new issue may be alleged as a reason to find a plan or plan amendment not in compliance in an administrative pleading filed more than 21 days after publication of notice unless the party seeking that issue establishes good cause for not alleging the issue within that time period. Good cause does not include excusable neglect. (§163.3184(5)(b)2., F.S.)
    5. The hearing on whether the plan or plan amendment is in compliance will be held by an administrative law judge in the affected local jurisdiction. (§163.3184(5)(c), F.S.)
      1. In challenges filed by an affected person, the comprehensive plan or plan amendment must be determined to be in compliance if the local government’s determination of compliance is fairly debatable. (§163.3184(5)(c)1., F.S.)
      2. In challenges filed by the state land planning agency, the local government’s determination that the comprehensive plan or plan amendment is in compliance is presumed to be correct and the local government’s determination will be sustained unless it is shown by a preponderance of the evidence that the comprehensive plan or plan amendment is not in compliance. (§163.3184(5)(c)2.a., F.S.)
      3. In challenges filed by the state land planning agency, the local government’s determination that elements of its plan are related to and consistent with each other will be sustained if the determination is fairly debatable. (§163.3184(5)(c)2.b., F.S.)
      4. In challenges filed by the state land planning agency that require a determination by the agency that an important state resource or facility will be adversely impacted by the adopted plan or plan amendment, the local government may contest the agency’s determination of an important state resource or facility. The state land planning agency must prove its determination by clear and convincing evidence. (§163.3184(5)(c)3., F.S.)
    6. Administrative law judge recommendation and final agency action.
      1. If the administrative law judge recommends that the amendment be found not in compliance, the judge must submit the recommended order to the Administration Commission for final agency action. The Administration Commission must enter a final order within 45 days after its receipt of the recommended order. (§163.3184(5)(d), F.S.)
      2. If the administrative law judge recommends that the amendment be found in compliance, the judge must submit the recommended order to the state land planning agency. (§163.3184(5)(d), F.S.)
        1. If the state land planning agency determines that the plan amendment should be found not in compliance, the agency must refer, within 30 days after receipt of the recommended order, the recommended order and its determination to the Administration Commission for final agency action. (§163.3184(5)(d)1., F.S.)
        2. If the state land planning agency determines that the plan amendment should be found in compliance, the agency must enter its final order not later than 30 days after receipt of the recommended order. (§163.3184(5)(d)2., F.S.)
  • Compliance Agreements
    1. The provisions are new language that replace, and borrow heavily from, the previous §163.3184(16), F.S., which is deleted.
    2. At any time after the filing of a challenge, the state land planning agency and the local government may voluntarily enter into a compliance agreement to resolve one or more of the issues raised in the proceedings. Affected persons who have initiated a formal proceeding or have intervened in a formal proceeding may also enter into a compliance agreement with the local government. (§163.3184(6)(a), F.S.)
    3. All parties granted intervenor status must be provided reasonable notice (the statute doesn’t say by whom) of the commencement of a compliance agreement negotiation process and a reasonable opportunity to participate in such negotiation process. (§163.3184(6)(a), F.S.)
    4. Negotiation meetings with local governments or intervenors are open to the public. (§163.3184(6)(a), F.S.)
    5. The compliance agreement must list each portion of the plan or plan amendment that has been challenged and specify remedial actions the local government has agreed to complete within a specified time to resolve the challenge, including adoption of all necessary plan amendments. (§163.3184(6)(a), F.S.)
    6. The compliance agreement may also establish monitoring requirements and incentives to ensure that the conditions of the compliance agreement are met. (§163.3184(6)(a), F.S.)
    7. Before its execution of a compliance agreement, the local government must approve the compliance agreement at a public hearing advertised at least 10 days before the public hearing in a newspaper of general circulation in the area, in accordance with the advertisement requirements of chapter 125 or chapter 166, as applicable. (§163.3184(6)(c), F.S.)
    8. The local government must hold a single public hearing for adopting remedial amendments. (§163.3184(6)(d), F.S.)
    9. The state land planning agency must provide each party granted intervenor status a copy of the compliance agreement within 10 days after the agreement is executed. (§163.3184(6)(a), F.S.)
    10. Upon the filing of a compliance agreement, executed by the parties to the challenge and the local government, with the Division of Administrative Hearings, any administrative proceeding under ss. 120.569 and 120.57 on the plan or plan amendment covered by the compliance agreement must be stayed. (§163.3184(6)(b), F.S.)
    11. For challenges to amendments adopted under the expedited review process, if the local government adopts a comprehensive plan amendment pursuant to a compliance agreement, an affected person or the state land planning agency may file a revised challenge with the Division of Administrative Hearings within 15 days after the adoption of the remedial amendment. (§163.3184(6)(e), F.S.)
    12. For challenges to amendments adopted under the state coordinated process, the state land planning agency, upon receipt of a plan or plan amendment adopted pursuant to a compliance agreement, will issue a cumulative notice of intent addressing both the remedial amendment and the plan or plan amendment that was the subject of the agreement. (§163.3184(6)(f), F.S.)
      1. If the local government adopts a comprehensive plan or plan amendment pursuant to a compliance agreement and a notice of intent to find the plan amendment in compliance is issued, the state land planning agency will forward the notice of intent to the Division of Administrative Hearings and the administrative law judge will realign the parties in the pending proceeding. The proceeding will then be governed by the “affected person” provisions contained in paragraph (5)(a) and subparagraph (5)(c)1. (§163.3184(6)(f)1., F.S.)
      2. Parties to the original proceeding at the time of realignment may continue as parties without being required to file additional pleadings to initiate a proceeding, but may timely amend their pleadings to raise any challenge to the amendment that is the subject of the cumulative notice of intent, and must otherwise conform to the rules of procedure of the Division of Administrative Hearings. (§163.3184(6)(f)1., F.S.)
      3. Any affected person not a party to the realigned proceeding may challenge the plan amendment that is the subject of the cumulative notice of intent by filing a petition with the agency as provided in subsection (5). The agency will forward the petition filed by the affected person not a party to the realigned proceeding to the Division of Administrative Hearings for consolidation with the realigned proceeding. (§163.3184(6)(f)1., F.S.)
      4. If the cumulative notice of intent is not challenged, the state land planning agency must request that the Division of Administrative Hearings relinquish jurisdiction to the state land planning agency for issuance of a final order. (§163.3184(6)(f)1., F.S.)
      5. If the local government adopts a comprehensive plan amendment pursuant to a compliance agreement and a notice of intent is issued that finds the plan amendment not in compliance, the state land planning agency must forward the notice of intent to the Division of Administrative Hearings, which will consolidate the proceeding with the pending proceeding and immediately set a date for a hearing in the pending proceeding under ss. 120.569 and 120.57. (§163.3184(6)(f)2., F.S.)
      6. Affected persons who are not a party to the underlying proceeding under ss. 120.569 and 120.57 may challenge the plan amendment adopted pursuant to the compliance agreement by filing a petition pursuant to paragraph (5)(a). (§163.3184(6)(f)1., F.S.)
    13. The compliance agreement provisions do not prohibit a local government from amending portions of its comprehensive plan other than those that are the subject of a challenge. However, such amendments to the plan may not be inconsistent with the compliance agreement. (§163.3184(6)(g), F.S.)
    14. The compliance agreement provisions do not require settlement by any party against its will or preclude the use of other informal dispute resolution methods in the course of or in addition to the method described in this subsection. (§163.3184(6)(h), F.S.)
  • Mediation and expeditious resolution.
    1. At any time after the administrative challenge has been forwarded to the Division of Administrative Hearings, the local government proposing the amendment may demand formal mediation, informal mediation, or expeditious resolution of the amendment proceedings. An affected person who is a party to the proceeding may demand informal mediation or expeditious resolution of the amendment proceedings. The demands are made by serving written notice on the state land planning agency, if the agency is a party to the proceeding, all other parties to the proceeding, and the administrative law judge. (§163.3184(7)(a), F.S.)
    2. Upon receipt of a notice of such a demand, the administrative law judge must set the matter for final hearing no more than 30 days after receipt of the notice. Once a final hearing has been set, no continuance in the hearing, and no additional time for post-hearing submittals, may be granted without the written agreement of the parties absent a finding by the administrative law judge of extraordinary circumstances. Extraordinary circumstances do not include matters relating to workload or need for additional time for preparation, negotiation, or mediation. (§163.3184(7)(b), F.S.)
      1. This provision seems to only apply to the demand for expeditious resolution (especially in light of the tight time frame and the last word of the last sentence), not the demands for formal or informal mediation, even though it purports to apply to all.
    3. Absent a showing of extraordinary circumstances, in an administrative challenge case, the administrative law judge must issue a recommended order within 30 days after filing of the transcript, unless the parties agree in writing to a longer time. (§163.3184(7)(c), F.S.)
    4. Absent a showing of extraordinary circumstances, in an administrative challenge case, the Administration Commission must issue a final order within 45 days after the issuance of the recommended order, unless the parties agree in writing to a longer time. (§163.3184(7)(d), F.S.)
  • Administration Commission
    1. The provisions of former subsection (11), now subsection (8), are substantially unchanged, with mainly changes to reflect the new cross references.
    2. One substantive change is to clarify that the sanctions the commission may specify are those to which the local government will be subject if it elects to make the plan amendment effective notwithstanding the determination of noncompliance. (§163.3184(8)(b), F.S.)
  • The Good Faith Filing and Exclusive Proceedings provisions of former subsections (12) and (13), respectively, now subsections (9) and (10), respectively, are unchanged.
  • Public Hearings
    1. The provisions of former subsection (15), now subsection (11), are substantially unchanged, with mainly changes to reflect the new cross references and cross references to the notice being published pursuant to the relevant provisions of chapter 125 for counties or chapter 166 for municipalities.
    2. One change is to move the language from previous §163.3187(5), F.S. that says nothing in the provisions is intended to prohibit or limit the authority of local governments to require an amendment applicant to pay some or all of the cost of the public notice. (§163.3184(11)(c), F.S.)
  • Process for adoption of small-scale comprehensive plan amendments. (§163.3187)
    1. An allowed small-scale amendment is a future land use map amendment for a site-specific small scale development activity of 10 acres or fewer acres, where the annual cumulative acres of small scale amendments by that local government is not in excess of 120 acres and the amendment property is not located within an area of critical state concern (with limited exceptions). (§163.3187(1), F.S.)
      1. A text change that relates directly to the small scale land use map amendment may be adopted simultaneously. (§163.3187(1)(c), F.S.)
      2. The provisions of previous §163.3187(c)1.a.(I) – (III), F.S., which varied the maximum acreage by specific types of areas or factors in the jurisdiction, are deleted.
      3. The provisions of previous §163.3187(c)1.f., F.S., addressing limitations on small scale amendments involving residential land uses, are deleted.
    2. The provisions of previous §163.3187(c)2.a., F.S., addressing public notice requirements, are deleted.
    3. The provisions requiring only one public hearing for the adoption of a small scale amendment remain, with minor modifications. (§163.3187(2), F.S.)
    4. The provisions allowing a doubling of the 10-acre limit for small scale amendment in a rural area of critical economic concern, in certain circumstances, remain, with minor modifications. (§163.3187(3), F.S.)
    5. Any affected person may file a petition to challenge the compliance of a small scale amendment under essentially the same provisions as the previous wording except the local government’s compliance determination, although no longer presumed to be correct, only needs to be shown to be fairly debatable and the state land planning agency may not intervene in a small scale amendment challenge. (§163.3187(5)(a), F.S.)
    6. The provisions of §163.3187(5)(b), F.S., addressing the actions by the administrative law judge and the final agency action on challenges of small scale amendments, are essentially unchanged.
    7. The effective date provisions are essentially unchanged. (§163.3187(5)(c), F.S.)
    8. A new provision was added which say, in all challenges of small scale amendments, in making a determination of compliance, consideration must be given to the plan amendment as a whole and whether the plan amendment furthers the intent of the statute. (§163.3187(5)(d), F.S.)
  • Concurrent zoning. The provisions of former §163.3184(3)(e), F.S., allowing the concurrent enactment of necessary zoning changes with plan amendment adoption, are moved, with minor amendments, to subsection 163.3184(12).
  • Effectiveness of plan amendments in Areas of Critical State Concern. The provisions of former §163.3184(14), F.S., stating an plan amendment applicable to a designated area of critical state concern will not be effective until a final order is issued finding the plan “in compliance,” are moved, with minor amendments, to subsection (13).
  • Subsection 163.3187(4) preserves the requirement that comprehensive plans may only be amended in such a way as to preserve the internal consistency of the plan. Because this provision is now under the small amendments section, rather than the general plan amendment section it was previously, it is not clear if the admonition only applies to small scale amendments or to all plan amendments.
  • The provisions of former §163.3184(15)(c) and (d), F.S., addressing sign-in forms at the transmittal and adoption hearings, are deleted.
  • The provisions of former §163.3184(15)(e), F.S., requiring plan amendments that change the actual list of allowable uses to be noticed in the same manner as an amendment to a land development regulations ordinance that does the same, are deleted.
  • The provisions of former §163.3184(17), (18), and (19), F.S., addressing community vision and urban boundary plan amendments, urban infill and redevelopment plan amendments, and housing incentive strategy plan amendments, respectively, are deleted.
  • The provisions of former §163.3187(4), F.S., requiring transmittal of copies of all plan amendments to the state land planning agency for the purpose of keeping the state files up to date, are deleted.
  • The provisions of former §163.3187(6), F.S., addressing plan amendments relative to evaluation and appraisal reports, are deleted.
  • The provisions of previous §163.3187(1)(d)-(q), F.S., addressing various exceptions to the limit on the frequency of adoption, are deleted.